OEE Optimization in the Production of Biochemical Active Ingredients
- 10% lower production costs
- 20% lower project costs
Manufacturing site for biochemical active ingredients with a single production line
OEE optimization at a manufacturing site for biochemical active ingredients whose single production line had reached its capacity limits. The goal was to make downtime losses transparent and to make better use of available production capacity.
The challenge
The situation
The manufacturing site had reached its capacity limits. Systematic OEE tracking was lacking, which resulted in a lack of transparency regarding downtime losses. Inefficient communication between the process teams and inadequate capacity planning aggravated the problem. Frequent production stoppages caused by time-consuming cleaning processes further disrupted operations. The main objectives were to optimize downtime-loss tracking, to improve communication between the teams, and to reduce cleaning times in order to minimize stoppages.
Our approach
How Entourage approached it
Planning of the entire development project through to market launch
Regular status reports and assessment of objective attainment, so that the newly captured OEE leads to decisions rather than merely being measured.
Weekly project meetings to steer the team, against the inefficient communication between the process teams.
Introduction of systematic downtime-loss tracking and optimization of capacity planning
Reduction of cleaning times and minimization of production stoppages
The outcome
What changed
The optimization led to a 10 percent reduction in production costs and improved capacity utilization. Within 12 months, project costs were reduced by 20 percent.
10% lower production costs
Reduction of production costs by 10 percent through more efficient use of production capacity.
Increased capacity utilization
Higher capacity utilization through improved team coordination and task management.
20% lower project costs
Reduction of project costs by 20 percent within 12 months.
Your next step
What this topic involves and how we work is set out on the topic page.
Lean Manufacturing →To start, the On-site Quick Check brings us to your site for one to three days to check the current state.
About the On-site Quick Check →Related expertise
Lean Manufacturing →
OEE measurability and efficient operations along the production line.
Continuous Improvement Programs →
Systematic downtime-loss tracking and sustainable process control.
Production Transfer & Scale-Up →
Better use of production capacity once capacity limits have been reached.
Lean Six Sigma →
Methodology for reducing downtime losses and production stoppages.
Similar projects
More on Biotech →Image notice: The images on this page were generated using artificial intelligence. They do not depict real people, places, or events.
Your project
A comparable project?
Briefly outline your situation. We'll respond with an initial assessment, usually within one business day.
Prefer direct? +49 89 4161170-0
contact@theentourage.de
- Reply usually within one working day
- 3 locations: DE · CH · IT · projects in the US too
- 100% life sciences